The electricity production of Skarta Energy’s solar park built in the Pälkänevesi industrial area started in the last week of August. The park will be commissioned in stages. At the first stage, about 1 MVA is connected to the network. Once completed, the entire park will produce 4.5 GWh of renewable solar power. The solar farm is the first renewable energy production plant in the Pälkäne region.
The final inspection of the building supervision of the solar park built in the Pälkänevesi industrial area was carried out during week 35, and now the park is connected to Elenia’s electricity network. Lumme Energia is responsible for electricity sales. The project has progressed on schedule. The municipality of Pälkäne and Skarta Energy signed a letter of intent on the construction of a solar park in June 2022. Construction of the park began in February 2024 and electricity production started in August 2024. The entire park is scheduled to be completed during 2024. Solarigo Systems Oy was responsible for the construction of the Pälkäne solar park.